ARTICLE SUBJECT PAGE - ------- ------- ---- I DESCRIPTION AND CLASSIFICATION 1
II CONTRACT PRICE AND TERMS OF PAYMENT 3
III DELAYS IN PERFORMANCE 8
IV APPROVAL OF PLANS AND DRAWINGS AND
INSPECTION DURING CONSTRUCTION 10
V MODIFICATIONS 12
VI TESTS AND TRIALS 15
VII DELIVERY DATE AND DELIVERY 18
VIII FORCE MAJEURE DELAYS 23
IX OWNER FURNISHED EQUIPMENT DELAYS 24
X WARRANTY OF QUALITY 25
XI CANCELLATION BY BUYER 28
XII SUSPENSION BY BUYER 30
XIII BUYER'S DEFAULT 32
XIV BUILDER'S DEFAULT 34
XV LIABILITIES AND INDEMNITIES 37
XVI INSURANCE 38
XVII DISPUTE AND ARBITRATION 41
XVIII RIGHTS OF ASSIGNMENT AND VESSEL RECIPIENT
DESIGNATION 43
XIX TAXES AND DUTIES 44
XX PATENTS, TRADEMARKS, COPYRIGHTS, ETC. 44
XXI ADDRESSES 45
XXII NOTICES AND LANGUAGE 45
3
INDEX
ARTICLE SUBJECT PAGE - ------- ------- ---- XXIII EFFECTIVE DATE OF CONTRACT 46
XXIV INTERPRETATION 46
XXV CONFLICT AND AUDIT 47
XXVI PUBLICITY RELEASES 49
EXHIBIT "A" SCHEDULE OF LABOR AND MATERIAL RATES
EXHIBIT "B" PROTOCOL OF DELIVERY AND ACCEPTANCE
EXHIBIT "C-1" IRREVOCABLE STAND-BY LETTER OF CREDIT
EXHIBIT "C-2" ON DEMAND PERFORMANCE BOND
EXHIBIT "D" CONTRACT SPECIFICATIONS
EXHIBIT "E" CONTRACT DRAWINGS LIST
4
CONTRACT FOR THE CONSTRUCTION AND SALE OF
A JACK-UP DRILLING UNIT
(HULL NO. 2001)
THIS CONTRACT, made effective this 1st day of February, 2001 by and between PPL Shipyard Pte. Ltd., a company organized and existing under the laws of Singapore, having its principal place of business located at 21 Pandan Road, Singapore 609273 (hereinafter called the "BUILDER") and Santa Fe International Corporation, a corporation organized and existing under the laws of the Cayman Islands, with an office at 5420 LBJ Freeway, Suite 1100, Dallas, Texas 75240, U.S.A. (hereinafter called the "BUYER" or "OWNER").
WITNESSETH:
WHEREAS, the BUILDER agrees to furnish all necessary labor and materials to design, construct, equip, complete and test, at its shipyard located at 21 Pandan Road, Singapore 609273 (hereinafter called the "Shipyard") and sell and deliver afloat at the Shipyard to the BUYER one (1) Freide and Goldman JU2000 jack-up drilling unit more fully described in Article I hereof (hereinafter called the "VESSEL"); and
WHEREAS, the BUYER agrees to purchase and accept delivery of the VESSEL at the Shipyard from the BUILDER and to pay for the same, all upon the terms and conditions hereinafter set forth.
NOW, THEREFORE, undertaking to perform each party's responsibilities and to exercise each party's rights with good faith in interpreting this Contract and the Specifications, the parties hereby agree, in consideration of the mutual promises and covenants hereinafter contained, as follows:
ARTICLE I - DESCRIPTION AND CLASSIFICATION
1. Description:
The VESSEL shall have the BUILDER's Hull No. 2001 and shall be designed, constructed, equipped and completed in accordance with the provisions of (i) this Contract, and (ii) the Contract Specifications attached to this Contract as Exhibit "D" and the Contract Drawings attached to this Contract as listed in Exhibit "E" (herein collectively called the "Specifications") signed by each of the parties hereto for identification on even date herewith and incorporated by reference and made an integral part hereof.
1 5
2. Dimensions and Characteristics:
The VESSEL is a Freide and Goldman JU2000 jack-up drilling unit which will bear BUILDER's Hull No. 2001 of approximate dimensions 231 feet long, 250 feet wide and 31 feet deep at the side. The details of the above particulars as well as the definitions and method of measurements and calculations are as indicated in the Specifications.
3. Classification, Rules and Regulations:
The VESSEL (including its machinery, equipment and outfitting) shall be constructed in accordance with good shipbuilding practices and with the American Bureau of Shipping's, (herein called the "Classification Society") Rules for Building and Classing Mobile Offshore Drilling Units (the edition and amendments thereto being in force as of the date of this Contract), the IMO MODU Code 1989, and other such specific requirements as are set out in this Contract and the Specifications, and the BUYER's satisfaction. Decisions of the Classification Society as to compliance or non-compliance with the Classification shall be final and binding upon both parties hereto.
The VESSEL shall also meet all requirements of the rules, regulations and requirements of the International Loadline Convention and other regulatory bodies as described in the Specifications in effect as of the date of this Contract. All fees and charges incidental to the classification and with respect to meeting the requirements of the above-referenced rules, regulations and requirements, as well as design fees and/or royalties shall be for the account of BUILDER.
4. Registration:
The VESSEL shall be registered by the BUYER at its own cost and expense under the laws of the Republic of Vanuatu with its home port at Port Vila, or such other place as the BUYER shall designate at the time of its delivery and acceptance hereunder. In addition, the BUYER reserves the right, at its sole discretion, to register the VESSEL under construction at its own cost and expense under the Laws of the Republic of Vanuatu or such other place as the BUYER may deem appropriate, at any time following payment of the first installment of the Contract Price.
5. Subcontracting:
The BUILDER may, with BUYER's written approval, which shall not be unreasonably withheld, at its sole discretion and responsibility subcontract any portion of the construction work of the VESSEL which is to be performed within the Republic of Singapore. Subject to BUYER's written approval, the BUILDER may, at its sole discretion and responsibility, subcontract any portion of the construction work of the VESSEL which is to be performed outside the Republic of Singapore. In any event, BUILDER shall retain full responsibility and liability
2 6
as if it did the work itself for any subcontracted work, including warranties, guarantees and schedule.
6. Permits and Observance of Applicable Laws:
BUILDER warrants that it is duly authorized with all applicable licenses (including but not limited to those required in respect of the Freide and Goldman JU2000 design) to construct, equip, complete, sell and perform the entirety of the work covered hereby and to deliver the VESSEL as provided for herein and that it will obtain in a timely manner all necessary permits, licenses, and authorizations required for performing such work and making such delivery. BUILDER further warrants that it and all of its subcontractors will observe all applicable laws, orders, decrees, ordinances, rules and regulations of the country of construction and of its subdivisions and all duly constituted government agencies having jurisdiction.
7. Design Responsibilities
It is expressly agreed and understood that the BUILDER shall be exclusively responsible for all aspects of the design and engineering required in respect of the construction, equipment and completion of the VESSEL in accordance with the provisions of this Contract and the Specifications. The BUILDER shall accordingly be responsible for any additional costs and expenses of construction, equipment and completion of the VESSEL beyond those originally envisaged at the time of signature hereof which result from any deficiency or shortcoming in the Freide and Goldman JU2000 design or any design or engineering undertaken to develop the same for the purposes of performance of this Contract.
However, the environmental ratings contained in Section 1.5 of the Specifications may be amended by official letter from ABS following their detailed review of the design. Such amendments, if any, will be deemed to be retroactively incorporated into Section 1.5 of the Specifications. The BUILDER shall be responsible for not exceeding the weights and heights of the vertical centers of gravity contained in Section 1.5.8 of the Specifications.
8. Notwithstanding any other provision of this Contract, specifically including but not limited to the Effective Date as defined in Article XXIII, BUILDER shall not commence construction of the VESSEL under this Contract prior to 1 March 2001 (the "Construction Commencement Date").
ARTICLE II - CONTRACT PRICE AND TERMS OF PAYMENT
1. Contract Price:
The contract price of the VESSEL is Seventy-Two Million Three Hundred Sixty-Nine Thousand Five Hundred United States Dollars (U.S. $72,369,500), receivable by the BUILDER (herein called the "Contract Price"), subject to upward or downward adjustment, if any, as set forth in this Contract. Provided, however, that the Contract Price shall be reduced by One Million Four Hundred Fifty-Two Thousand United States Dollars (U.S.$1,452,000) if the BUYER elects to reduce the VESSEL's leg length by fifty-six (56) feet should BUYER give notice of such election to BUILDER no later than ninety-one (91) calendar days after the Construction Commencement Date. Should BUYER give BUILDER later notice at any time up until the last fifty-six (56) feet of the leg sections begin to be installed on the VESSEL, then the Contract Price shall be reduced by Seven Hundred Two Thousand United States Dollars (U.S.$702,000) and BUYER shall have ownership of the leg chord material with BUILDER having ownership of the leg bracing material.
3 7 2. Currency:
Any and all payments required to be made by either party under this Contract shall be made in United States Dollars. Payments required to be made by BUYER to BUILDER shall be made as follows:
Citibank N.A., New York
For Account Citibank N.A., Singapore
Favoring: PPL Shipyard Pte. Ltd.
USD Account Number: 0-812872-028
3. Terms of Payment:
The Contract Price shall be paid by the BUYER to the BUILDER in installments as follows:
(a) 1st Installment:
The sum of Seven Million Two Hundred Thirty-Six Thousand Nine Hundred
Fifty United States Dollars (U.S.$7,236,950), equivalent to ten percent
(10%) of the Contract Price shall be paid upon the second banking day
next following the Construction Commencement Date or BUILDER's delivery
of both the irrevocable standby letter of credit and the on demand
performance bond to the BUYER as required under Article XI, Paragraph
2, whichever occurs later.
(b) 2nd Installment:
The sum of Fourteen Million Four Hundred Seventy-Three Thousand Nine
Hundred United States Dollars (U.S.$14,473,900), equivalent to twenty
percent (20%) of the Contract Price shall be paid upon the second
banking day next following the later of (i) the date on which the
BUILDER has executed and delivered to the BUYER the Assignment as
contemplated by Clause 8 of that certain Overall Agreement dated on or
about 1 February 2001 between the BUILDER and the BUYER together with
the approval and notification to Jurong Town Corporation in the
prescribed form (including the registration of the particulars of the
Assignment with the Registry of Companies and Businesses); or (ii)
laying the keel of the VESSEL, which shall be deemed to require
completion of the following tasks:
o Erection of completed inner bottom blocks 1C1 and 1C2 and
associated piping, 100% complete including successful NDT, and:
o Complete procurement of all main hull structure steel.
4 8
o Completion of fabrication / assembly of bulkheads for blocks
1C1 and 1C2, 100% complete including successful NDT.
o Completion of fabrication / assembly of inner bottom block
panels 1C3, 100% complete including successful NDT.
o Completion fabrication / assembly of bulkheads for block
1C3, 100% complete including successful NDT.
(c) 3rd Installment
The sum of Fourteen Million Four Hundred Seventy-Three Thousand Nine
Hundred United States Dollars (U.S.$14,473,900), equivalent to twenty
percent (20%) of the Contract Price shall be paid upon the second
banking day next following completion of the three leg well modules,
which shall be deemed to require completion of the following tasks:
o Completion of fabrication / assembly of the three leg well blocks
5, 6 and 7, 100% complete including successful NDT, including:
o Completion of fabrication / assembly of the three spud cans,
100% complete including successful NDT.
o Completion of fabrication / assembly of inner bottom blocks
1FS, 1AS, 1FP and 1AP, 100% complete including successful
NDT.
o Completion fabrication / assembly of bulkheads for blocks
1FS, 1AS, 1FP and 1AP, 100% complete including successful
NDT.
o Completion of erection of center block 1C1/1C2, 1C3, 100%
complete including successful NDT.
o Completion of fabrication / assembly of inner bottom blocks
8, 9, 11 and 12, 100% complete including successful NDT.
o Completion fabrication / assembly of bulkheads for blocks 8,
9, 11 and 12, 100% complete including successful NDT.
o 100% completion of detailed engineering drawings for
architectural outfitting and 60% of completion of mechanical
drawings.
(d) 4th Installment
The sum of Ten Million Eight Hundred Fifty-Five Thousand Four Hundred
Twenty-Five United States Dollars (U.S.$10,855,425), equivalent to
fifteen percent (15%) of the Contract Price shall be paid upon the
second banking day next following installation of the first section of
all three (3) legs on the VESSEL, which shall be deemed to require
completion of the following tasks:
o Completion of erection and weld out of all three 1st leg
rounds to the completed spud cans, 100% complete including
successful NDT sign off of the connection Work, and:
5 9
o Completion fabrication / assembly /machine / erection jack
foundations and bracing all three leg wells, 100% complete
including successful NDT.
o Completion fabrication / assembly / erection accommodation
blocks, 100% complete including successful NDT.
o Completion fabrication / assembly helicopter deck and
support structure, 100% complete including successful NDT.
o Completion fabrication / paint / installation steel
outfitting below main deck, 100% complete including
successful NDT.
o Complete blast and paint quarters.
o Completion erection of all remaining inner bottoms and
bulkheads, 100% complete including successful NDT.
o 100% completion of detailed engineering drawings for
structural, 70% completion for steel outfitting, piping and
electrical.
o Complete installation electrical cable ways hull, quarters.
(e) 5th Installment
The sum of Ten Million Eight Hundred Fifty-Five Thousand Four Hundred
Twenty-Five United States Dollars (U.S.$10,855,425), equivalent to
fifteen percent (15%) of the Contract Price shall be paid upon the
second banking day next following launching of the VESSEL which shall
be deemed to require completion of undocking and jackup the VESSEL
along side of wharf, including:
o Complete consolidation of vesseL hull, proven integrity of
hull compartments.
o Complete installation quarters equipment.
o Completion fabrication / assembly cantilever structure, 100%
complete including successful NDT.
o Completion fabrication / assembly / erection drill floor /
substructure, drawworks shelter / windwall and lower
derrick.
o Complete fabrication / assembly 2nd and 3rd round of legs.
o Complete fabrication / paint / installation of steel
outfitting and piping helideck, quarters.
o Complete installation machinery deck, intermediate deck and
jacking equipment.
o Complete fabrication / installation of HVAC ducting in hull.
o Complete fabrication / paint / installation piping systems
above / below main deck, quarters.
o Complete hydro test / flushing hull and quarters piping
systems.
o Complete fabrication / installation HVAC ducting in
accommodation blocks.
(f) 6th Installment
6 10
The sum of Seven Million Two Hundred Thirty-Six Thousand Nine Hundred
Fifty United States Dollars (U.S.$7,236,950), equivalent to ten percent
(10%) of the Contract Price shall be paid upon the second banking day
next following installation of the legs on the VESSEL which shall be
deemed to require completion of the following tasks:
o Complete fabrication / assembly and erection of 2nd, 3rd, 4th,
5th and 6th leg rounds for all 3 legs, 100% complete including
successful NDT sign off of the connection Work, including:
o Complete erection derrick.
o Complete erection helideck, cantilever, drill floor on main
hull.
o Complete installation helideck, drill floor and cantilever
equipment.
o Complete hydro test deep tanks.
o Complete installation maindeck equipment.
o Complete blast and paint cantilever, drill floor.
o Complete hull installation hull and accommodation
architectural outfitting. o Complete mechanical completion,
test and commissioning Marine systems.
o Complete fabrication / paint / installation piping systems
cantilever and drill floor piping systems.
o Complete installation electrical cable ways helideck,
cantilever and drill floor.
o Complete blast and paint drill floor, helideck and
cantilever.
o Complete fabrication / paint / installation steel outfitting
at maindeck and drill floor.
o Complete fabrication / installation / hydro test piping
systems in spud cans, legs.
o Complete hydro test flushing helideck, cantilever and drill
floor piping systems.
(g) 7th Installment
The sum of Seven Million Two Hundred Thirty-Six Thousand Nine Hundred
Fifty United States Dollars (U.S.$7,236,950), equivalent to ten percent
(10%) of the Contract Price, plus any increase or minus any decrease
due to adjustments of the Contract Price hereunder, shall be paid upon
the second banking day next following completion of the following
tasks:
o Complete install / terminate entire vessel electrical cables.
o Complete test and commissioning drilling systems, jacking trials
and incline experiment.
o Completion of compartment closeout and all the VESSEL works.
o Completion of all commissioning, tests and trials.
o Completion of all discrepancy punch lists.
7 11
o Completion of all certification and documentation.
o Complete VESSEL preparations necessary for load out.
o Complete loading of all VESSEL materials and warehouse.
o Completion and delivery of all Delivery Documentation.
and execution by the parties of the PROTOCOL OF DELIVERY AND ACCEPTANCE
pursuant to Article VII(2) hereof.
For avoidance of doubt and for purposes of satisfying the intent of each of the above-described payment milestone events, they shall not be deemed to have been fulfilled until such time as all prerequisite tasks and activities associated with such milestone as described on the BUILDER's Construction Schedule have been fully completed.
As used herein, the term "banking day" shall mean any day in which commercial banks are open for business in Texas or New York and Singapore.
At least two (2) banking days in advance of the due date of each installment payment, BUILDER shall give both the BUYER and the BUYER's Representative written notice by facsimile or registered mail. Each installment notice shall state: (i) the stage of work achieved as defined by the BUILDER's Construction Schedule as defined in Article IV, Paragraph 1(c); (ii) that the work completed complies with the Plans, Specifications and this Contract; (iii) that there are no liens or claims upon the VESSEL. Each installment notice shall be executed by an officer of the BUILDER. If BUILDER has any outstanding liens on the VESSEL, BUYER shall not be obligated to make such payments until the liens are resolved.
ARTICLE III - DELAYS IN PERFORMANCE
1. Delivery:
(a) If any delay in construction of the VESSEL, excepting only Permissible
Delays, should continue for a period of one hundred eighty (180)
calendar days during construction (as determined by reference to the
BUILDER's Construction Schedule defined in Article IV, Paragraph 1
(c)), then in such event, the BUYER may at its option cancel this
Contract at any time thereafter in accordance with the provisions of
Article XI hereof. The BUILDER may, at any time after the expiration of
the aforementioned one hundred eighty (180) calendar days of delay
during construction, if the BUYER has not served notice of cancellation
as provided in Article XI hereof, demand in writing that the BUYER
shall make an election, in which case the BUYER shall, within thirty
(30) calendar days after such demand is delivered to the BUYER, notify
the BUILDER of its intention either to cancel this Contract or to
consent to the acceptance of the VESSEL at an agreed future date; it
being understood by the parties
8 12
hereto that, if the VESSEL is not delivered by such future date or if
construction is again delayed for one hundred eighty (180) calendar
days or more (as determined by reference to the BUILDER's Construction
Schedule defined at Article IV, Paragraph 1(c)), the BUYER shall have
the same right of cancellation upon the same terms and conditions as
hereinabove provided.
(b) If the VESSEL is not delivered by the thirty-first (31st) calendar day
after the Delivery Date (as such term is defined in Article VII,
Paragraph 1(a)) for any reason, excepting only force majeure delays (as
defined in Article VIII) and Permissible Delays ...
*End of Preview*