Between Owner And Contractor

Effective Date: September 01, 1994
Parties:

Cerner

Sectors: Services
EXHIBIT 10(w)(iii)


AMENDMENT NO. 1
to the
AGREEMENT
BETWEEN OWNER and CONTRACTOR


MODIFICATION and AMENDMENT


made as of the 24th day of October in the year Nineteen Hundred and Ninety- Four.


Between the Owner: Cerner Properties, Inc.
2800 Rockcreek Parkway, Suite 601
Kansas City, Missouri 64117
and the Contractor: J. E. Dunn Construction Company
929 Holmes
Kansas City, Missouri 64106


The Project: Cerner Associate Center
2800 Rockcreek Parkway
Kansas City, Missouri 64117


The Architect: Hollis & Miller Group
309 SW Market Street
Lee's Summit, Missouri 64063-2315


The Owner and the Contractor agree as set forth below:


Whereas, the Owner and Contractor have previously agreed to amend their Agreement to establish a scope, costs, schedule and Contract Documents, and


Whereas, the Owner and Contractor now wish to so amend their Agreement,


NOW, THEREFORE, in consideration of the mutual covenants and conditions contained herein, the parties hereto agree to Amendment of their Contract dated September 1, 1994, as set forth below:


1. This Amendment No. 1 is for the Early Bid Package.


2. In accordance with Paragraphs 4.1 and 4.2, the Date of Commencement
shall be the date of this Amendment and the substantial completion date
shall be pursuant to a mutually agreed upon Contractor's project
schedule.
3. In accordance with Paragraphs 5.2 and 5.3 of the Agreement, the
Guaranteed Maximum Price for the Work of this Amendment shall be
established as: Three Million Three Hundred Thirty Two Thousand
One Hundred Thirty Nine Dollars ($3,332,139.00), which includes
deductive value engineering alternates 1 through 9 totaling
$224,600.00.


Pursuant to Paragraphs 5.1 and 5.3, the Contractor's Fee
applicable to the work of this amendment shall be established as:
Ninety Seven Thousand One Hundred Fifty Eight Dollars ($97,158.00) 4. Pursuant to Paragraphs 16.13 through 16.17 of the Agreement, the
Contract Documents describing the Scope of Work of this Amendment and
upon which the G.M.P. stated in Item #3 above is based, are as follows:
Paragraph Description Title Date --------- ----------- ------- ------ 16.1.3 Supplementary & Cerner Associate August 22, 1994
Other Conditions Center - Early (Ref. Exhibit A)
Bid Package
Project Manual


16.1.4 Specifications Cerner Associate August 22, 1994
Center - Early (Ref. Exhibit A)
Bid Package
Project Manual


16.1.5 Drawings Cerner Associate August 22, 1994
Center - Early (Ref. Exhibit A)
Bid Package


16.1.6 Addenda No. 1 September 8, 1994
No. 2 September 15, 1994


16.1.7 Other Documents Proposal & October 25, 1994
Clarifications
(9 pages)


This Modification and Amendment entered into as of the day and year first written above.


OWNER: CONTRACTOR:


CERNER PROPERTIES, INC. J. E. DUNN CONSTRUCTION COMPANY


BY:/s/Clifford W. Illig BY:/s/Barrett Brady
Barrett Brady
Executive Vice President


EXHIBIT A ----------


1. Contract between Owner and Contractor dated September 1, 1994.


2. General Conditions, AIA Document A201, as supplemented and included
in the Project Manual.


3. Drawings dated August 22, 1994, listed as follows:


C1.1 through C5.2
S100 through S302
A0.0, A0.2, A1.1, A2.1 through A2.5, A6.1 through A6.5, A7.1
through A7.6, A8.1, A11.1, A11.3
M1.1 through M1.4
P1.1 through P1.4
ME1.1, E1.1 through E1.4
SP-1 through SP-5


4. Project Manual dated August 22, 1994 titled Cerner Associate Center-
Early Bid Package Project Manual.


5. Addenda
-------
No. 1 dated September 8, 1994
No. 2 dated September 15, 1994


October 25, 1994


Mr. Steve Lee Cerner Corporation 2800 Rock Creek Parkway Kansas City, Missouri 64117


Re: Cerner Associates Center
J. E. Dunn Project No. 821


Dear Steve:


Enclosed for your review is a copy of our Guaranteed Maximum Price proposal for the Early Bid Package on the above referenced project. With assistance of the Hollis & Miller Group, we have provided recommended value engineering alternates which bring the cost of the work within the + 5% of the median range estimate figure.


We have also had the opportunity to look forward and project the Final Bid Package costs. From our cost projections it is apparent that the project has evolved to a level higher than our schematic ...

*End of Preview*